Name | Length | Frequency | QFD Attendees | Client Attendees | Agenda | ||||
---|---|---|---|---|---|---|---|---|---|
Welcome Call | 1HR | Once, Transitioning from Sales to Onboarding | Account Executive Project Manager DRE Manager | Sale Group/Client Account Executives Project Manager Business and Technology Team Leads |
| ||||
DRE Project Kick Off Review | 1HR | Once, Post-Welcome Call | Project Manager DRE Manager | Project Manager Business and Technology Team Leads |
| ||||
Manager TouchbaseGovernance Meeting | 15-30MIN | Weekly, throughout full project | Project Manager DRE Manager (as needed) | Project Manager | Review Project Plan, dates and deliverables to ensure go live is safe Share applicable project updates 30-45MIN | Monthly | CRO EVP Manager of PMO PM | Executive(s) Project Sponsor PM |
|
Tech Required Inputs Calls | 30MIN | Weekly, During Required Inputs Stage | Project Manager Technology & Integration SME | Project Manager Technology Team |
| ||||
Business Required Inputs Calls | 30MIN | Weekly, During Required Inputs Stage | Project Manager Product Consultant SME | Project Manager Business Team |
| ||||
DRE Project Implementation Calls30MINOperational Readiness Series | 1HR | Weekly, During Implementation Stage(Bi-Weekly, DRE Focused) | Project Manager DRE Manager | Project Manager Operations Team DRE Manager As Needed:Technology & Integration SME Product Consultant SME |
| ||||
Implementation Touchbase | 30MIN | Weekly, During Implementation | Project Manager DRE Manager (as needed) | Project Manager As Needed: |
| ||||
System Demo | 1HR | Once, Early Implementation | Training Specialist | Project Manager Fraud and Dispute Managers Training Team Interested Leadership |
| ||||
QFD Claim Preparedness | 30MIN | Once, Early Implementation | Training Specialist | Project Manager Claim Management Team Interested Leadership |
| ||||
Intake Training | 1 - 1.5 HRS | Once, Mid-Implementation | Training Specialist | Project Manager Front office Team Testing Team |
| ||||
Back Office Review | 90 MIN | Once, Prior to Go-Live | Project Manager DRE Manager Training Specialist | Project Manager Project Leaders Back office Team Operations Leadership |
| ||||
Go-Live Preparedness Trainings | 2HR | Once, Prior to Go-Live | Training Specialist | Project Manager Trainers Leadership Reporting Users |
| ||||
Communications Center Training | 30MIN | Once, Prior to Go Live | Project Manager | Project Manager Business and Technology Team Leads |
| ||||
Launch Preparation Call | 30MIN | Daily for 1-2 weeks leading up to and following Go Live | Project Manager DRE Manager Client Success Manager | Project Manager Business and Technology Team Leads |
| ||||
Transition Call | 30MIN | Once, After Quavo Certification is Complete | Project Manager Client Success Manager DRE Manager Support Manager | Project Manager Post-Production Business and Technology Team Leads |
|
...