Add-On Project Calls
Name | Length | Frequency | QFD Attendees | Client Attendees | Agenda |
---|---|---|---|---|---|
Required Inputs Review | 30MIN | Once to begin the add-on project | Project Manager | Project Manager Business and Technology Team Leads |
|
Project Touchbase | 15-30MIN | Weekly, throughout full project | Project Manager As Needed: | Project Manager As Needed: |
|
Governance Meeting | 30-45MIN | Monthly | CRO EVP Manager of PMO PM | Executive(s) Project Sponsor PM |
|
New Product Training(s) (Varies by Add-Ons) | Varies | Once, Mid-Implementation | Training Specialist | Project Manager Applicable Team based on Topic |
|
Transition Call | 30MIN | Once, after Quavo Certification | Project Manager Client Success Manager Support Manager | Project Manager Post-Production Business and Technology Team Leads |
|